Second ‘bathtub’ grant won’t fix Parkway East flooding before 2026

For the second time in a week, the overflowing Monongahela River has closed the area of the Parkway East in Downtown Pittsburgh known as “the bathtub.”

To address the situation, which occurs when water rises high enough to flood the Monongahela Wharf and overwhelms the flood wall, the federal Department of Transportation has awarded two grants this year worth $45.6 million, including $6.7 million this week.

Unfortunately, the extra money won’t result in the Pennsylvania Department of Transportation fixing the problem any sooner.

That’s because the project to expand the wall has been in preliminary engineering and won’t move to final design until later this year, said PennDOT spokesman Steve Cowan. As a result, it probably won’t be put out for construction bids until summer or fall 2026.